Frontline Service: Training Procedure
Category: COMPLEX
Scope: This procedure covers all the trainings to be conducted to the Balanga City, Municipalities of Dinalupihan, Hermosa, Orani, Samal, Abucay, Pilar, Orion, Mariveles, Limay, Bagac and Morong, schools, private sectors, hospitals and other agencies in the Province of Bataan.
How to Avail of the Service:
STEP | APPLICANT/CLIENT | SERVICE PROVIDER | DURATION OF ACTIVITY | PERSON IN CHARGE | DOCUMENTS NEEDED |
1 | LGU’s | Monitor (Log and Post) the advisory from DOST- PAGASA / PHIVOLCS, etc | 1 hour | Operation Division / LDRRM Assistant | Hazard Monitoring Logsheet / PDRRMO Facebook Account / Bulletin Board |
2 | LDRRMO’s | Obtains initial status from the City / Municipalities | 2 hours | Operation Division / LDRRM Assistant | Monitoring Logbook |
3 | Convene the PDRRMC and conduct Pre – Disaster Risk Assessment (PDRA) (as need arises) | 1 day | PDRRM Officer | Pre – Disaster Risk Assessment (PDRA) Report | |
4 | Prepare the final report and provide report to the PDRRM Officer | 1 hour | PDRRM Officer | Situational Report | |
5 | Activate the Emergency Operation Center (EOC) (as need arises) | 1 day | PDRRM Officer | Incident Command System Forms (202,203,204,205,206,207,208 and 211) | |
6 | Conduct Rapid Damage Assessment and Needs Analysis (RDANA) (as need arises) | 2-3 days. | PDRRM Officer/Team | Rapid Damage Assessment Needs Analysis (RDANA) Report Form | |
7 | Continuous Monitoring | 2 hours | Operation Division / LDRRM Assistant | ||
8 | Conduct Damage Assessment and Needs Analysis (DANA) (as need arises) | 1 – 2 weeks after the disaster | PDRRM Officer/Team | Damage Assessment and Needs Analysis (DANA) Report | |
9 | Prepare the final report and provide report to the PDRRM Officer | 1 day | LDRRM Assistant | ||
10 | Conduct Demobilization (as need arises) | 1 day | PDRRM Officer | ICS Form No. 221 (Demobilization Form) | |
11 | Conduct Post Disaster Needs Assessment (as need arises) | 2 – 3 months | PDRRM Officer/Team | Post Disaster Needs Assessment (PDNA) Report | |
12 | Formulate the strategic Recovery and Rehabilitation (RR) and Plan (as need arises) | 1 – 2 weeks. | PDRRM Officer / Vice – Chairperson for Recovery and Rehabilitation (PPDO) | Recovery and Rehabilitation and Plan (RRP) | |
13 | Monitor the implementation of the Recovery and Rehabilitation Projects (as need arises) | 1-5 years depending on the magnitude of disaster | PDRRM Officer / Vice – Chairperson for Recovery and Rehabilitation (PPDO) | Report on the Implementation of RR Projects |
Mandate: Implements required actions and measures pertaining to all aspects of disaster risk reduction and management, including good governance, risk assessment and eariy warning knowledge building and awareness raising, reducing underlying risk factors and preparedness for effective response and early recovery.
Josefina T. Timoteo - Provincial Disaster Risk Reduction and Management Officer
2/F 1Bataan Command Center, Brgy. Doña, Orani, Bataan Philippines
Mon – Fri: 8:00 am – 5:00 pm